Earthwork End-Area / Prismoidal Calculator

Estimate cut/fill earthwork volume between two cross-section areas using the average end-area and prismoidal methods.

Your inputs

Change any value to update the result instantly.

Construction & Materials
m

Prismoidal volume

750 m³

Average end-area volume

750 m³

Prismoidal correction

0 m³

Volume in cubic yards

981 yd³

Formula and working

V(end-area) = (A1+A2)/2 × L; V(prismoidal) = L/6 × (A1+4Am+A2)

  1. 1

    Collect the inputs

    Cross-section area 1 = 20 m²; Mid-section area = 25 m²; Cross-section area 2 = 30 m²; Distance between sections L = 30 m

  2. 2

    Apply the formula

    V(end-area) = (A1+A2)/2 × L; V(prismoidal) = L/6 × (A1+4Am+A2)

  3. 3

    Result

    Prismoidal volume = 750 m³

Frequently asked questions

Important limitation

This is an educational estimate based only on the values and formula shown. Verify current rates, rules, units, and professional standards before relying on the result. It is not personalized financial or investment advice.