Boiler Blowdown Rate from TDS Calculator
Calculate required boiler blowdown rate to keep feedwater TDS or silica within limits.
Your inputs
Change any value to update the result instantly.
Blowdown rate
84.7 lb/hr
Blowdown percentage
1.69 %
Feedwater rate
5,000 lb/hr
Boiler TDS limit
3,000 ppm
Formula and working
Blowdown % = Feedwater TDS ÷ (Boiler TDS limit − Feedwater TDS) × 100
- 1
Collect the inputs
Feedwater rate = 5,000 lb/hr; Feedwater TDS = 50 ppm; Boiler TDS limit = 3,000 ppm
- 2
Apply the formula
Blowdown % = Feedwater TDS ÷ (Boiler TDS limit − Feedwater TDS) × 100
- 3
Result
Blowdown rate = 84.7 lb/hr
Frequently asked questions
Important limitation
This is an educational estimate based only on the values and formula shown. Verify current rates, rules, units, and professional standards before relying on the result. It is not personalized financial or investment advice.
Report a mistake or request an improvement
Tell us if a formula, unit, explanation, or result needs attention. Your message will include this calculator’s name and page.
Related calculators
Acid Rain Neutralisation Calculator
Estimate the mass of calcium carbonate slurry needed to neutralise a given volume of acidic rainwater.
Carbon Tax Cost Calculator
Calculate the total carbon tax cost owed from tons of CO2e emitted and the applicable tax rate.
Chilled Water GPM from Tonnage Calculator
Calculate required chilled water flow rate in GPM from cooling tonnage and design temperature difference.
Compressed Air Leakage Loss Calculator
Estimate CFM lost to compressed air leaks and the resulting annual energy cost.
Condenser Water Flow Rate Calculator
Estimate condenser water flow requirement using the standard 3 GPM per ton rule of thumb.
Cooling Tower Evaporation & Blowdown Calculator
Estimate evaporation, drift and blowdown water losses in a cooling tower from circulation rate and cycles of concentration.